Almost ₴1 million will be spent on the adjustment of the reconstruction project of a part of the waterworks in Mykolaiv
- News of Mykolaiv
-
•
-
- Yuliia Boichenko
-
•
-
8:00, 23 September, 2024
The Mykolaiv Regional Military Administration plans to spend 943.1 thousand hryvnias on the adjustment of the reconstruction project of the city water supply.
This is evidenced by the data of the ProZorro public procurement system, reported NikVesti.
It is a water pipe with a diameter of 1,000 millimeters from 2nd Sichova Street to Prymiska Street in the Korabelnyi district of Mykolaiv. The Department of Architecture and Capital Construction of the Mykolayiv Regional State Administration concluded a contract for the adjustment of the reconstruction project with Concord Project LLC.
Club NikVesti — a place where the reader and the editorial team are on the same side.
Members have access to a private chat, an exclusive newsletter with behind-the-scenes stories from journalists, see the news earlier, and influence the changes.
Join us. Together we keep the city bright
The recipient of donations is the NGO “Mykolaiv Media Hub” (EDRPOU 45160758). By making a donation, you confirm that the amount is non-refundable and may be used by the NGO to implement its statutory activities, including supporting independent journalism and creating socially significant content. Public offer.
The company has already concluded three contracts with the regional military administration: one for the reconstruction of the duiker in the Soliani microdistrict ( 1.4 million hryvnias ) and two for the reconstruction of the water pipeline in Korabelnyi district: from the sewage treatment plant to the 2nd Sichova ( 1.4 million hryvnias ) and from 2nd Sichova Street to Prymiska Street ( 1.4 million hryvnias ). At the same time, this contractor developed a project to build a residential complex in Pervomaisk for 10 million hryvnias and a project to rebuild Lyceum №60 in Varvarivka.
The contractor must complete the adjustment of the water main reconstruction project by December 31, 2024.
The adjustment of the project is necessary in order to specify the location of the pipeline route, specified NikVesti in the Department of Architecture and Capital Construction of the Mykolaiv region.
«In the process of earthworks, it became clear that the existing routes have a different route of laying and cross the projected water main several times at different points. As a result, the pipeline laying profile was adjusted,» they explained.
At the same time, RMA added, because of this, it is necessary to additionally install shut-off valves and make switching chambers.