Almost ₴1 million will be spent on the adjustment of the reconstruction project of a part of the waterworks in Mykolaiv

Pipes for replacing part of the water network in Mykolaiv, photo «NikVesti" Pipes for replacing part of the water network in Mykolaiv, photo NikVesti

The Mykolaiv Regional Military Administration plans to spend 943.1 thousand hryvnias on the adjustment of the reconstruction project of the city water supply.

This is evidenced by the data of the ProZorro public procurement system, reported NikVesti.

It is a water pipe with a diameter of 1,000 millimeters from 2nd Sichova Street to Prymiska Street in the Korabelnyi district of Mykolaiv. The Department of Architecture and Capital Construction of the Mykolayiv Regional State Administration concluded a contract for the adjustment of the reconstruction project with Concord Project LLC.

The company has already concluded three contracts with the regional military administration: one for the reconstruction of the duiker in the Soliani microdistrict ( 1.4 million hryvnias ) and two for the reconstruction of the water pipeline in Korabelnyi district: from the sewage treatment plant to the 2nd Sichova ( 1.4 million hryvnias ) and from 2nd Sichova Street to Prymiska Street ( 1.4 million hryvnias ). At the same time, this contractor developed a project to build a residential complex in Pervomaisk for 10 million hryvnias and a project to rebuild Lyceum №60 in Varvarivka.

The contractor must complete the adjustment of the water main reconstruction project by December 31, 2024.

The adjustment of the project is necessary in order to specify the location of the pipeline route, specified NikVesti in the Department of Architecture and Capital Construction of the Mykolaiv region.

«In the process of earthworks, it became clear that the existing routes have a different route of laying and cross the projected water main several times at different points. As a result, the pipeline laying profile was adjusted,» they explained.

At the same time, RMA added, because of this, it is necessary to additionally install shut-off valves and make switching chambers.

 

Чому ви читаєте «МикВісті»? Яка наша діяльність найбільш важлива для вас? Та чи хотіли б ви стати частиною спільноти читачів? Пройдіть опитування, це анонімно і займе 5 хвилин вашого часу

Read more:

0
Discussion

To join the conversation, please to the NikVesti website.

We’ve launched the NikVesti Club!

Community of readers, who believe in the power of media and change reality through journalism

Our goal is 200
Already 1 NikVesti readers have joined the Club